Compliance guide
Patch management: what the official guidance says
Patch management is the routine of finding, testing and installing updates. Sweden’s NCSC says the aim should be to install security updates “as soon as they are published”, and MCFFS 2026:11 requires covered operators to carry them out promptly in IT segments. This page compares NCSC, NIST and CISA, shows which timelines exist and who they bind, and how to prioritise.
On this page
This is a plain-language summary, not legal advice. Where this page and the law differ, the law decides. Sentences that start with “Our view” are our own advice, not the source’s. Swedish texts are quoted in our own English translation, which is not official.
1. In short
- Patch management is the standing routine for finding, testing and installing updates. Our wording; NIST’s guide calls the wider job “preventive maintenance for technology”.
- Swedish NCSC says the aim should be to install security updates “as soon as they are published”, starting with systems that are exposed to the internet, business-critical, or have vulnerabilities at risk of being exploited (recommendation 2; our translation).
- In Sweden, MCFFS 2026:11 requires covered operators to carry out security updates “skyndsamt” (promptly) in IT segments (4 kap. 31 §). It sets no number of days. A general advice (not binding) says to begin the work within 72 hours after a fix is available.
- NIST SP 800-40 Rev. 4 asks each organisation to set its own timeframes in maintenance plans. CISA’s deadlines (BOD 26-04) bind US federal civilian agencies only.
- This page is about the standing routine. For acting on one advisory see Information security news: how to act on a security advisory. For zero-days see Zero-day vulnerabilities.
2. What the official guides say
| Source | What it says |
|---|---|
| NCSC Sweden, recommendation 2 | Take an inventory of all information systems and their need for security updates, including firmware, drivers, operating systems and applications. Prioritise the most exposed systems, those with high CVSS scores or under active exploitation. If an update cannot be installed at once, take temporary protective measures. Combine manual methods, such as monitoring the news, with tools such as vulnerability scanning. Evaluate whether an update needs testing first. Automate installation where possible. Install only updates verified from the vendor, digitally signed and fetched over a protected connection (our translation). It adds that delaying makes the job bigger because updates pile up. |
| NIST SP 800-40 Rev. 4 (April 2022) | Patching is one of several ways to respond to risks from software vulnerabilities; the guide names four types of risk response: accept, mitigate, transfer, avoid (section 2.1). Installing a patch or upgrading are “the only forms of risk response that can completely eliminate the vulnerabilities without removing functionality”, but patching at once “is sometimes not viable”. Keep software inventories up to date and approach patching per asset (3.2). Define scenarios, group assets and give each group a maintenance plan (3.3–3.5). Choose metrics (3.6). |
| CISA, KEV catalog page and BOD 26-04 | CISA “strongly recommends” that all organisations review and monitor the KEV catalog and prioritise remediation of the listed vulnerabilities. Federal civilian agencies must follow BOD 26-04 (10 June 2026), which revokes BOD 22-01. CISA says organisations not bound by it can still strengthen their security by prioritising KEV entries. |
3. What timelines actually exist
Where a number exists, it binds only the people named.
| Source | Timeline | Binds |
|---|---|---|
| NIS2 | No number of days. Measures must include “vulnerability handling and disclosure” (Article 21(2)(e)). Recital 58: “swiftly identifying and remedying such vulnerabilities is an important factor in reducing risk”. | Essential and important entities (recital: explains the law, is not an article) |
| MCFFS 2026:11, 4 kap. 31 § | Security updates “skyndsamt” (promptly) to protect systems in IT segments. Software that the supplier no longer provides security updates for must be replaced or upgraded “utan onödigt dröjsmål” (without undue delay). For OT segments (cyber-physical systems) the operator must identify and handle the need for updates and upgrades. | Covered operators, within the scope limit below |
| Same section, general advice | Begin the work of introducing a security update within 72 hours after software that protects against the vulnerability has been made available. It says begin, not finish. | Not binding |
| MCFFS 2026:11, 4 kap. 30 §, general advice | Software should be updated to the latest version “without undue delay”. The operator should decide what to do when an update cannot be carried out or an ongoing change must be stopped. | Not binding |
| CISA BOD 26-04 | Remediation deadlines in its Table 1, in calendar days, depending on four things: whether the asset is publicly exposed, KEV status, whether an attacker can automate the exploit, and technical impact. | US federal civilian agencies, not contractors unless the contract says so |
| NIST SP 800-40 Rev. 4 | No single deadline in the text read. A maintenance plan defines “the timeframes for beginning and ending each action” (3.5). | Guidance |
Scope limit for MCFFS 2026:11 (1 kap. 1 §, second paragraph): operators that only carry on sector activity in digital infrastructure, digital providers, ICT service management (business-to-business), postal and courier services or space are subject only to the management-training rule in 2 kap. 1 §. The patching rule above does not apply to them. A stricter rule in another regulation takes precedence (1 kap. 2 §). The rule book came into force on 1 October 2026. MCF issued it; from 1 July 2026 the power to issue such rules (38–39 §§ of the ordinance) moved to FRA, and FRA says the rule books “gäller oförändrat” (apply unchanged). See Does NIS2 apply to my company?
4. How to prioritise
The three official sources use different inputs. Our view: use them together, and write the order down.
| Question | Where it comes from |
|---|---|
| Is it in use? | NCSC: inventory first. NIST 3.2: keep inventories up to date. It says that updating them monthly or quarterly by a vulnerability scan is a model that “should no longer be used”. |
| Is it reachable from the internet? | NCSC: prioritise exposed systems. BOD 26-04: “Asset Exposure” is one of four variables. |
| Is it being exploited? | NCSC: “active exploitation”. CISA: the KEV catalog. BOD 26-04: “KEV Status”. |
| How bad is the outcome? | NCSC: high CVSS scores. BOD 26-04: “Technical Impact”. NIST 3.4: an asset’s maintenance needs include the level of impact if vulnerable software is compromised. |
| What does this asset do? | NIST 3.2: decide per asset, using its technical and mission or business characteristics. NCSC: business-critical systems. |
For KEV, CVSS and EPSS side by side see how to act on a security advisory.
5. Building the routine
Steps in NIST’s order, with the Swedish rule that touches each. The Swedish rules bind covered operators only (scope limit above).
| Step | NIST SP 800-40 Rev. 4 | MCFFS 2026:11 |
|---|---|---|
| 1. Inventory | 3.2: constantly maintained software and asset inventories. | 4 kap. 9 §: keep an up-to-date list of relevant information about the digital environment, to be able to handle vulnerabilities and incidents “skyndsamt”. |
| 2. Scenarios | 3.3: routine patching, emergency patching, emergency mitigation, unpatchable assets. | 4 kap. 30 §: structured and traceable change management for installing, upgrading and updating hardware and software in the production environment. |
| 3. Groups and plans | 3.4–3.5: maintenance groups, each with a plan per scenario. Phased rollout to a small set of “canary” assets first should be considered for routine patching. | Not set out as a duty. General advice to 4 kap. 30 §: decide what to do when an update cannot be done. |
| 4. Check | 2.3.3–2.3.4: verify deployment and monitor. | 4 kap. 27 §: security tests must check that systems are updated to the latest approved version and that published vulnerabilities are handled (IT segments). |
| 5. Measure | 3.6: actionable metrics. NIST says metrics that are too simple are generally not actionable. | 3 kap. 4 §: management is informed about the measures and the level of cybersecurity when needed, and at least once a year. |
6. When you cannot patch
- NCSC: take temporary protective measures if an update cannot be installed immediately (our translation).
- NIST 3.5.4: plan long-term mitigation besides patching for unpatchable assets, review the alternatives periodically, and track exceptions to plans (3.5.5). Its examples of why an asset may be unpatchable (3.3) include the vendor not providing patches, such as end-of-life, and a need to run uninterrupted for an extended period.
- MCFFS 2026:11, 4 kap. 11 §, general advice (not binding): operators should put systems with vulnerabilities that cannot be handled satisfactorily in their own segments (our translation of the list item).
- MCFFS 2026:11, 4 kap. 31 §: software with no more security updates must be replaced or upgraded without undue delay.
7. How SimpleSecurity helps
SimpleSecurity does not install patches and does not make anyone compliant. It helps with the “what is in use and what is wrong with it” side.
| Duty | Service | What it does |
|---|---|---|
| Inventory | Asset Database (CMDB) | The single source of truth asset database, with per-asset posture badges. |
| Find known vulnerabilities | Vulnerability Scanner | Scheduled and on-demand CVE matching with KEV/EPSS threat context, plus port scanning. |
| Decide and track | Risk Register | A CVSS/EPSS-informed register that converts identified vulnerabilities into tracked, owned risks. |
8. Sources
- NCSC: 2. Installera säkerhetsuppdateringar skyndsamt
- NIST SP 800-40 Rev. 4, Guide to Enterprise Patch Management Planning (April 2022)
- CISA: Reducing the Significant Risk of Known Exploited Vulnerabilities
- CISA: BOD 26-04, Prioritizing Security Updates Based on Risk (10 June 2026)
- Directive (EU) 2022/2555 (NIS2), Article 21(2)(e) and recital 58
- MCFFS 2026:11, 1 kap. 1–2 §§, 3 kap. 4 §, 4 kap. 9, 11, 27, 30 and 31 §§, in force 1 October 2026